Driver Check-In, Seal Verification, and Gate Control
Gate and driver management procedure covering the single controlled entry point for carriers, identity and appointment verification before a trailer comes on site, inbound seal verification against the shipping paperwork with a seven-point trailer inspection where the facility performs one, seal removal witnessed and recorded, the driver waiting area and the rule that drivers do not walk the warehouse, outbound seal application and recording on the bill of lading, controlled seal stock with a numbered issue log, and the discrepancy stop-and-escalate rule that applies the moment a seal number does not match.
- Audience
- The gate or guard staff, the dock and shipping supervisors, the receiving and shipping clerks who verify and apply seals, the yard spotter, and every carrier driver entering the site
- Review cycle
- semiannual
- Last reviewed
- 2026-08-29
- Revision
- 1
What is in the procedure
8 sections. Regulatory language is fixed and passes through verbatim. Sections marked customized get rewritten around your facility, your equipment, and your job titles.
- 01
Purpose
FixedThis procedure controls the gate: who and what comes onto this site, what is verified before a trailer is worked, and how the integrity of a sealed load is established on arrival and preserved on departure.
- 02
Scope
CustomizedThis procedure applies to every carrier arrival and departure at this site: inbound loaded trailers and containers, outbound loaded trailers and containers, empty trailer drops and pulls, parcel and courier vehicles...
- 03
Responsibilities
CustomizedThe gate or guard staff verify identity, check the appointment and paperwork, record the arrival, verify and record the seal on an inbound loaded trailer, issue the driver badge and the site rules, and direct the driver...
- 04
Procedure: Arrival, Identity, Appointment, and Paperwork
Customized1. Every vehicle enters through the single designated entry point.
- 05
Procedure: Inbound Seal Verification, Trailer Inspection, and Seal Removal
Customized1. An inbound loaded trailer or container arriving sealed is checked at the gate before it is spotted at a door.
- 06
Procedure: Driver Conduct, the Waiting Area, and Trailer Control at the Dock
Customized1. Drivers do not enter the warehouse. This is the single rule that most reduces pedestrian risk and cargo exposure at a dock, and it holds for the regular driver everyone knows as much as for a stranger.
- 07
Procedure: Outbound Sealing, Documentation, and Seal Stock Control
Customized1. A loaded outbound trailer is sealed before it leaves the door, by the named authorized person, immediately after the load is verified complete and the doors are closed.
- 08
References
FixedThe gate log recording every arrival and departure with driver, carrier, tractor, trailer or container, seal numbers, and times.
Best practice
Driver Check-In, Seal Verification, and Gate Control: no regulation to cite
No public-domain regulation governs this procedure, so it cites nothing rather than inventing authority. It documents the process discipline customers, insurers, and auditors ask to see in writing.
Compliance checklist
What an inspector looks for
Every vehicle entered through the single designated gate, and all other gates were found closed and secured
Every arrival on the gate log records driver name verified from photo identification, carrier, tractor, trailer or container number, purpose, and time, and every departure is closed out with a time and the outbound seal number
Each arrival was verified against an appointment, tender, pickup number, or matching paperwork before admission, and unmatched arrivals were held at the gate for supervisor confirmation
Every driver received the site rules and a badge, wears high-visibility clothing outside the cab, and no driver was found in the warehouse
Every inbound sealed trailer had its seal physically checked and its number read and compared to the paperwork before being spotted at a door, with the number recorded on the gate log and the receiving record
No trailer with a seal discrepancy or a missing seal was opened; it was held, photographed, and escalated to the supervisor and the customer within the required timeframe
Where the facility or a customer requires a trailer or container inspection, it was performed systematically and recorded on the form for that trailer, with anomalies escalated before unloading
Seal removal was authorized, witnessed, and recorded with the number, the door, the person, and the time, and the removed seal was retained until the receipt reconciled
Empty trailers presented for loading were inspected for cleanliness and structural condition and refused at the gate if unfit
Trailers at a door are under dock control with chocks or a restraint applied, and no trailer was moved or released without the dock supervisor's release
Every outbound loaded trailer was sealed at the door immediately after load verification, with the seal type the customer requires, and the number recorded on the BOL, the shipping record, and the gate log
Seal stock is stored locked, issued by number against a log naming the recipient and shipment, reconciled on the stated cadence with every gap explained, and void seals are recorded and destroyed
Related templates
All Dock templates- DockRev 1
Trailer Chocking and Spotting
Securing trailers and trucks at loading docks before entry, covering wheel chock placement, dock lock engagement and...
- Regulatory references
- 1 CFR refs
- Sections
- 8 sections
- Review cadence
- annual review
- DockRev 1
Yard Truck and Trailer Movement
Yard spotter operations for moving trailers between the gate, the parking rows, and the dock, covering yard truck...
- Regulatory references
- 6 CFR refs
- Sections
- 10 sections
- Review cadence
- annual review
- DockRev 1
Dock Daily Safety Inspection
Start-of-shift safety walk of every dock position, covering levelers and dockboards, vehicle restraints and wheel...
- Regulatory references
- 6 CFR refs
- Sections
- 8 sections
- Review cadence
- quarterly review
- DockRev 1
Dock Plate and Leveler Operations
Safe deployment, use, and stowing of dock levelers and portable dock plates, covering lip engagement verification...
- Regulatory references
- 4 CFR refs
- Sections
- 8 sections
- Review cadence
- annual review
Free trial
Generate this SOP for your facility
Answer the facility questionnaire once and this template comes back with your equipment, your titles, and your sign-off sheet attached.
14-day free trial, no credit card. Launch pricing locked for a year.
This page is informational and is not legal advice. Have a qualified safety professional review any procedure before it goes into service at your facility.